Project Wise Progress Report of PV Solar Home System (SHS) installation |
|
Sl. No
|
Name of Project
|
Project Location
|
Project Target (Nos.)
|
Total Progress upto March’12 (Nos.)
|
|
a
|
b
|
c
|
d
|
e
|
|
1
|
Diffusion of Renewable Energy Technologies
|
Narshingdi-2
|
Pilot Project
|
14,000
|
|
2
|
Diffusion of Renewable Energy Technologies-2nd phase
|
12 PBS’s
|
1,200
|
|
3
|
Rural Electrification Through Solar Energy (IDA)
|
06 PBS’s
|
11,000
|
|
4
|
New consumer connection as per govt. rule (up to 31.03.12)
|
70 PBS’s
|
-
|
7,185
|
|
Total =
|
21,185
|
Summary of System Capacity:
|
System and Capacity
|
Quantity installed
|
|
System-1 (40 Wp)
|
14,000 Nos.
|
|
System-2 (50 Wp)
|
|
System-3 (80 Wp)
|
|
System-4 (100 Wp)
|
|
New consumer connection (Up to 31.03.2012)
|
7,185 Nos.
|
|
Total Household connection=
|
21,185 Nos.
|
Summary:
|
1
|
Installed Capacity
|
745.00 KWp
|
|
2
|
New consumer connection (Up to 31.03.2012)
|
658.00 KWp
|
|
3
|
REB Head Quarter Building Rooftop Solar Power Plant
|
49.00 KWp
|
|
Total =
|
1452.00 KWp
|
|