মেনু নির্বাচন করুন
Text size A A A
Color C C C C
সর্ব-শেষ হাল-নাগাদ: ২১st মে ২০১৮

এক নজরে বাপবিবোর্ড এর কার্যক্রম

                                                                                                         (as on April' 2018)

 

1

Total PBSs

80 Nos.

2

Approved Projects

78 Nos.

3

District included in RE program

61 Nos.

4

Upazillas included in RE program

460 Nos.

5

100% Energized Upazillas

61 Nos.

6

Villages included in RE program

83,303Nos.

7

Villages energized

73,583 Nos.

8

House Hold in Program Area

2,51,68,763 Nos.

9

Population in Program Area

10,68,93,673 Nos.

10

Line constructed 

3,96,364 Km

11

Line energized

3,90,402 Km

12

Number of 33/11KV Sub-station & Capacity

804 Nos. & 9120 MVA

13

System loss (80 PBSs)

10.89% (12 Month Avg), 8.75% (This Month)

14

Monthly Sales

Tk 1250 Crore

15

Bill collection

98.22%

16

Peak demand

6200 MW

 

17. Consumer (By category):

1) LT-A (Domestic)

2,02,27,474

2) LT-B (Irrigation)

2,72,613

3) LT-C1 (Small Industry)

1,56,341

4) LT-C2 (Construction)

505

5)  LT-D1 (Charitable Institute)

2,82,129

6) LT-D2 (Street Light)

20,669

7) LT-E (Commercial )

14,41,180

8) LT-T ( Temporary)

610

9) MT-1 ( Domestic)

80

10) MT-2 (Commercial)

880

11) MT-3 (Industry )

11,652

12) MT-4 (Construction)

76

13) MT-5 (General)

350

14) MT-6 ( Temporary)

64

15) HT-1 (General )

7

16) HT -2 ( Commercial)

0

17) HT-3 ( Industry )

269

18) HT-4 (Construction)

0

19) EHT-1 (General)

0

20) EHT-2 (General)

0

21) Solar 

14,266

Total

2,24,29,165

Ref: April-March, 2018 & Line Construction Report

 


Share with :